In Slovakia, in the city of Martin in Žilinský Region, our company implemented a newly built upper section of a new operations building for investor PMR, s.r.o.
The new operations hall construction consisted of installing a steel 27.6 x 57.6 m frame skeleton, dimensioned with crane rails for two overhead traveling cranes of load bearing capacities of 8 tons and 16 tons. Our scope of works included the delivery of both overhead cranes.
The project further involved the installation of roof composite cladding, including a thermally insulated valley gutter, delivery of external wall cladding, roof and wall windows and doors, metalwork and sheetmetal fittings.
The successfully completed project was accepted by the investor for use.
| Investor: | PMR, s.r.o. |
| Year: | 2018 |
| Total duration: | 3 months |
| Built-up area: | 1590 m² |