We took part in the construction of the new headquarters of HV Výtahy s.r.o. in Opava which included the construction of the new production facilities and it was only 5 km from our headquarters.

At the end of 2018, our company started the construction of the first part of the superstructure skeleton of the new production hall with an administrative building. The solution for the entire construction of the production premises was designed and implemented in our VEDE construction system, using a light lattice system clad with horizontally laid sandwich panels.

This new construction of production facilities was then further expanded at the end of 2019 with a side extension which was again designed in our VEDE construction system.

 

This production facility and the client’s front administrative offices form the company’s new headquarters with a total built-up area of ​​1,468 m2.

The construction of the superstructure included the delivery and installation of all windows, doors, gates and skylights as well as all sheet metal and ironmongery.

This project has been included in our portfolio of production halls.

The work was successfully completed and handed over to the client.

Investor: HV Výtahy s.r.o.
Year: 2018/2019/2020
Total duration: 6,5 months
Built-up area: 1468 m²